Floor plenum airtightness
In July 2016, BSRIA published BG65/2016 Floor Plenum Airtightness – Guidance and Testing Methodology. This replaced BG 12/2010 Floor Void Airtightness – Air Leakage Specification,
Since the introduction of airtightness testing as part of the Building Regulations, the air leakage of buildings has steadily reduced as construction teams have become more familiar with the requirements. By introducing lower specifications for floor plenums, it is hoped that the effect will be similar.
A floor plenum is a void between a building’s floor structure and a raised access floor, used for distributing conditioned air to the spaces above.
It is important that conditioned air in a floor plenum flows into the occupied zone and does not leak into cavities, risers, stairwells, heating trenches or other adjacent zones. A properly sealed floor plenum will allow the diffusers and grilles to fulfill their primary role of delivering air at the correct flow rate. As a result, the airtightness of floor plenums can be a serious energy efficiency issue.
BSRIA’s new guide addresses these issues and places upper limits on the air leakage of floor plenums. Distinctions are made between air leakage to adjacent spaces (normally referred to as plenum leakage), and uncontrolled air leakage into conditioned zones (normally referred to as raised access floor leakage). A testing methodology for both plenum leakage and raised access floor leakage is given, and guidance on achieving both is provided.
To download or purchase the guide, go to the BSRIA Bookshop.
N.B. This guide replaces BG 12/2010 Floor Void Airtightness – Air Leakage Specification, which was withdrawn.
--BSRIA
[edit] Related articles on Designing Buildings Wiki
- Air tightness in buildings.
- Airtightness of energy efficient buildings.
- BSRIA articles on Designing Buildings Wiki.
- Building performance evaluation.
- Closing the gap between design and as-built performance.
- Draughts in buildings.
- Energy Performance Certificates.
- Indoor air quality.
- Performance gap.
- Plenum ventilation in buildings.
- Thermographic survey.
- The history of non-domestic air tightness testing.
Featured articles and news
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.
Setting Expectations on Competence Management
Industry Competence Committee.
New Scottish and Welsh governments
CIOB stresses importance of construction after new parliament elections.
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.